Award site work contracts - mid-August 2008
Site work complete - November 2008
Award Construction contracts - mid March 2009
Construction complete - May 2010
Move in - June 2010
School starts - August 25, 2010
Award site work contracts - mid-August 2008
Site work complete - November 2008
Award Construction contracts - mid March 2009
Construction complete - May 2010
Move in - June 2010
School starts - August 25, 2010